Milestone
|
Dependencies
|
5 July 2016
|
Test current build process. Does it meet file
naming requirements as noted by Chet?
|
Waiting on info from Chet
|
29 July 2016
|
Complete work on content model generation
Complete work on SEO and Google analytics
|
|
1 - 5 August 2016
|
Build draft DITA 1.3 errata for TC review
|
|
8 - 12 August 2016
|
Internal TC (DITAweb) review of errata (5
days)
|
|
15 - 19 August 2016
|
Build Committee Draft Specification (5 days)
|
|
Tuesday, 23 August 2016
|
Adopt corrections (and updated spec) as a
Committee Draft Specification; request 15-day public review
|
|
23 August - 5 September 2016
|
OASIS staff prepares materials for 15-day
public review (14 days)
|
|
6 - 20 September 2016
|
15-day public review
|
|
21 - 26 September 2016
|
Editors respond to 15-day public review
comments (4 days)
|
|
Tuesday, 27 September 2016
|
TC approves DITA DITA 1.3 errata
|
|
27 September - 14 October 2016
|
OASIS staff prepare DITA 1.3 errata for
publication (14 days)
|
|
Monday, 17 October 2016
|
TC Admin announces DITA 1.3 errata |
|