Subject: Committee Specification Dates
On today’s call I took an action item to present some possible time times for the completion of the specification. The following is the process time line, followed by some work-back to show a possible committee specification date:
1. Agreed committee specification – requires 2/3 approval 2. 30 day public review 3. Submit to board for approval by 15th of month 4. Last day of following month – voting closed 5. 2 Weeks admin 6. OASIS standard
So, if we agree a committee specification by May 15th we get a standard on/around July 15th…